1. Preparation
Good preparation ensures the best results.

  • Allow the Click-PVC planks to acclimatise in the room for 48 hours , in closed packaging (18–25 °C).

  • The surface must be flat, dry, clean, and stable . If the surface is uneven, exceed 2 mm per meter, level it.

  • For concrete floors : moisture content max. 2% and always use a moisture barrier (foil) .

  • For wooden floors: make sure everything is properly secured and does not bounce.

  • Humidity: 45–65% .

  • Always use a suitable underlay for Click-PVC (sound insulation + leveling).

Tools required:
spacers • pencil • try square • tape measure • rubber mallet • stop block • utility knife or PVC saw
(Laminate cutters are not suitable.)

2. How to lay the Click-PVC floor

  • Mix planks from different packs for a natural distribution of colours.

  • Start in a corner. Place the groove side against the wall and use 5 mm spacers.

  • First, click in the long side , then the end . Work row by row.

  • Preferably lay in the direction of the light .

  • Obstacles such as pipes can be easily cut and made to fit.

  • Always maintain an expansion joint of 5 mm at doorways and transitions.

  • Cut the last row to size. Place the plank upside down against the previous row, mark it, cut/saw, and click it into place.

3. Finishing

  • Finish with skirting boards :

    • high skirting boards on the wall

    • or skirting boards (degrease the surface first).

  • Neatly tuck the edges of the subfloor foil under the skirting boards.

  • The floor is ready for use as soon as it is laid.